How-to Payments
How staged payments should work
In brief
Staged or progress payments are instalments paid as defined parts of the job are finished. The rule in every state is the same in spirit: pay for work done, not for time passed or work to come. Victoria and the Northern Territory publish set percentages for each stage of a new house, and Queensland and Tasmania bar a builder from claiming more than half the price before half the work is complete.
A building contract is a long exchange of money for work, and the schedule of payments decides who is carrying the risk at each point. Paid ahead of the work, you are an unsecured lender to your builder. Paid in step with it, a builder who stops tomorrow leaves you with roughly what you have paid for.
The stages of a house
Victoria defines the stages in law, and its definitions are a useful vocabulary anywhere.
- Base. For a timber floor, the concrete footings are poured and the base brickwork is built to floor level, or the stumps, piers or columns are complete. For a slab, the floor is complete.
- Frame. The frame is completed and approved by a building surveyor.
- Lock-up. External wall cladding and roof covering are fixed, the flooring is laid and external doors and windows are fixed, even if only temporary ones.
- Fixing. Internal cladding, architraves, skirtings, doors, built-in shelves, baths, basins, troughs, sinks, cabinets and cupboards are fitted and fixed in position.
Note what "frame" requires. The stage is not complete when the last stud is nailed. It is complete when the surveyor has approved it.
What the law sets
| Jurisdiction | Rule |
|---|---|
| Victoria | For a contract to build all stages: 10% at base, 15% at frame, 35% at lock-up, 25% at fixing, after the deposit |
| Northern Territory | Standard schedule caps: 5% deposit, 10% base, 20% frame, 25% enclosed, 30% fixing, 7% practical completion, at least 3% after occupancy certification |
| Queensland | Payments must be relative to work completed; no more than 50% of the price, deposit included, until 50% of on-site work is done |
| Tasmania | No more than 50 per cent of the price until at least half the work has been completed |
| New South Wales | Contracts over $20,000 must contain a progress payment schedule, and payments must match work done |
| South Australia | Payment only when work is substantially complete, requested in writing |
Victoria's percentages change where the contract covers only part of the build. To lock-up, the schedule is 20 per cent at base and 25 per cent at frame. To fixing, it is 12, 18 and 40 per cent. Consumer Affairs Victoria says to get legal advice before agreeing to anything different. In the Territory an alternative schedule must be recorded as a formal agreement on the prescribed forms.
Victoria's contract law is being amended, with the new rules due by 1 December 2026 and progress payment stages to be set in regulations, so check the current figures before relying on that row.
Before you pay each claim
Consumer Affairs Victoria's checklist is three lines long: the work has passed the building surveyor's inspection, it meets your contract requirements, and it is complete. Ask the builder or surveyor for a written copy of each inspection report.
For a renovation that has no neat stages, write your own into the contract and tie each to something you can see: demolition complete and site cleared; frame and roof on; rough-in of plumbing and electrical inspected; linings fixed; practical completion. Put a dollar figure beside each. NSW's advice is to make sure the value placed on each stage is realistic. A schedule that asks for 40 per cent on "commencement of framing" has been written by the builder's bank manager.
On a large job, NSW suggests paying an independent consultant or architect to inspect before each payment, at a cost it puts between $250 and $500 an inspection.
What not to do
Do not pay early as a favour. Victoria's regulator warns that warranty cover may not extend to work paid for before it is completed, and its new Home Warranty scheme may reduce assistance where progress payments were made before stages were finished. South Australia says extra or early staged payments are not covered by its insurance.
Do not stop paying on your own judgement either. Consumer Affairs Victoria advises against withholding a progress payment because of defects without first getting legal advice, because a wrongly withheld payment can put you in breach.
Sources
- Deposits and payments for building work, Consumer Affairs Victoria
- During construction checklist, Consumer Affairs Victoria
- New domestic building contract laws passed in Victoria, Consumer Affairs Victoria
- Time limits and amounts for Home Warranty, Building and Plumbing Commission
- Signing a residential building contract, Northern Territory Government
- Deposits and progress payments, QBCC
- Residential Building Consumer Guide, CBOS Tasmania
- Contracts for residential building work, NSW Government
- Building, extending and renovating a home, Consumer and Business Services (SA)
State rules mentioned here are set out in full on our licensing pages: Victoria, Northern Territory, Queensland, Tasmania, New South Wales.