Handover: what to check before the final payment

In brief

Before you make the final payment, inspect the work against the contract, list any defects in writing, and collect the certificates: a Certificate of Final Inspection or Occupancy Permit in Victoria, an occupation certificate in NSW, and compliance certificates for plumbing, gas and electrical work. The final payment is your last practical hold over the builder, so make it once the paperwork is in your hands.

The last week of a building job has its own momentum. The builder wants the final claim paid and the trailer off site. You want your house back. Both pressures push toward a quick walk-through and a handshake, and that is how owners end up chasing a missing certificate for six months.

Practical completion

The QBCC explains the term: practical completion means your home is mostly finished and ready for use. You do a final inspection with your builder to list any minor defects, which the builder must fix within a reasonable timeframe.

"Practical completion" is a contract term, and what it means depends on the definition in yours. Consumer Affairs Victoria is wary enough of the phrase to suggest that if you find it in a contract, you delete it and insert "complete in accordance with the plans and specifications". Whatever your contract says, read the definition before the inspection so you know what standard you are inspecting to.

In Tasmania the building contractor must give you a notice advising the date of practical completion within 10 business days. Warranty periods run from that date, so file the notice.

The inspection

Allow two hours for a house and do it in daylight. Bring the contract, the plans, the specification and every signed variation. Consumer Affairs Victoria's standard is the right one: check that everything in your contract is delivered and in working order before making the final payment, and that all works defined in the plans and specifications are completed to the agreed standard.

Work through the house in a fixed order so nothing is skipped.

  • Outside. Roof, gutters and downpipes connected; flashings; external paint; paths falling away from the house; site clean.
  • Every room. Open and close each door and window. Look along the walls and ceilings in raking light. Check paint, skirtings and floor finishes.
  • Wet areas. Run every tap, hot and cold. Fill and empty basins and the bath. Run the shower for several minutes and check the floor drains toward the waste. Flush toilets.
  • Electrical. Test every power point and switch. Press the test button on each safety switch and each smoke alarm.
  • Appliances and fittings. Confirm brands and models against the specification. Turn each one on.
  • Under and above. Put your head into the roof space and, on a raised house, the subfloor. Insulation complete, no rubbish left, no ducts disconnected.

Write each item down with its location. Victoria's consumer regulator suggests paying an independent building consultant to check for defects or unfinished work at this point, and handover is the inspection most worth paying for.

The documents

The QBCC's description of handover is that you receive keys, certification documents and warranties, and that you should ensure all inspections are certified and documents provided before final payment. Consumer Affairs Victoria lists what to hold in that state:

  • a Certificate of Final Inspection for extensions and renovations, or an Occupancy Permit for new homes, issued by your building surveyor;
  • any other certificates required, such as glazing or termite protection.

Add to that list, wherever you are:

  • the plumbing compliance certificate, which in Victoria only a licensed plumber can issue;
  • the gas certificate, such as the certificate of compliance or certificate of inspection a NSW gasfitter must give you;
  • the electrical certificate, in Victoria a Certificate of Electrical Safety;
  • the waterproofing statement and photographs for each wet area;
  • the home warranty insurance certificate, if you do not already hold it;
  • manuals and manufacturers' warranties for appliances, hot water, heating and cooling;
  • the durable termite notice, which the building code requires to be fixed in a prominent place such as the meter box.

Victoria adds an obligation of your own. If the final cost of the work has increased by $15,625 or more, the owner must notify the Building and Plumbing Commission within 28 days of becoming aware.

The final payment

The Northern Territory's standard schedule builds in the principle that matters here: the final instalment, at least 3 per cent of the contract price, is payable after the occupancy certification has been issued. Elsewhere, your contract sets the trigger. Read it. If the final payment falls due at practical completion, minor defects may be dealt with during the defects period that follows; if it falls due only on completion in accordance with the plans and specifications, the list should be cleared first.

Either way, exchange the last payment for the last document. Once the account is settled, the builder's incentive to return a phone call about a missing certificate falls sharply.

After handover

Tell your home insurer the work is finished. NSW notes that if the value of your home has increased as a result of renovations, you may wish to increase the sum insured.

Then start a file: contract, variations, certificates, inspection reports, the handover defects list and photographs. Statutory warranties run for years, and they pass to whoever buys the house from you.

Sources

  1. Finalising the work, QBCC
  2. When building work is complete checklist, Consumer Affairs Victoria
  3. Building contracts, Consumer Affairs Victoria
  4. Engaging a plumber, Building and Plumbing Commission
  5. Certificates of Electrical Safety, Energy Safe Victoria
  6. Using a gasfitter for repairs or building work, NSW Government
  7. Insurance requirements for contractors working on your home, NSW Government
  8. Residential Building Consumer Guide, CBOS Tasmania
  9. Signing a residential building contract, Northern Territory Government
  10. NCC 2022 Housing Provisions, Part 3.4 Termite risk management, Australian Building Codes Board