How-to Contracts
How to use a cooling-off period on a building contract
In brief
Most states give you five business days to withdraw from a home building contract after signing, though the trigger and the contract value differ. Withdrawal must be in writing, and in Queensland and Tasmania the builder may keep $100 plus reasonable out-of-pocket expenses. The ACT has no cooling-off period at all.
Cooling-off rights exist because building contracts are often signed in a hurry: at a display home, at the kitchen table with a salesperson waiting, or under the pressure of a price "only good until Friday". NSW lists that last tactic among its warning signs and calls it what it usually is, a sales pitch.
What each jurisdiction gives you
| Jurisdiction | Period | Applies to |
|---|---|---|
| New South Wales | Five clear business days after you are given a copy of the contract | Contracts valued over $20,000 |
| Victoria | Five days after signing | Lost if you get independent legal advice before signing |
| Queensland | Five business days | Contracts over $3,300 |
| South Australia | Five clear business days | Described in the CBS guide for new home contracts |
| Tasmania | Five business days | Contracts of $20,000 or more |
| ACT | No cooling-off period | The ACT Government says none is mandatory for building contracts |
The regulator pages we read for Western Australia and the Northern Territory did not state a cooling-off period for building contracts, so in those places check the contract itself and ask the regulator.
When the clock starts
The period does not always run from the signature.
In Queensland it begins the day after you receive a signed copy of the entire contract, including plans and specifications, and, for contracts of $20,000 or more, a copy of the QBCC Consumer Building Guide. The QBCC points out that if the contractor delays giving you any of these, the period in which you can withdraw is prolonged.
In Tasmania it runs from when you receive the signed contract with its plans and specifications and the Residential Building Consumer Guide, which the builder must provide within 5 business days of signing.
In New South Wales it runs from being given a copy of the contract. NSW counts business days strictly for contract purposes: weekends, public holidays and 27 to 31 December are excluded when working out the five business days in which the builder must give you your copy.
How to withdraw
Do it in writing, sign it, and be able to prove when it was delivered.
Queensland sets the form. You must give the contractor a written and signed withdrawal notice stating that you are withdrawing under the cooling-off provisions in section 35 of Schedule 1B of the QBCC Act. Use those words. South Australia's Form 1, which the builder must give you, explains how to serve a cooling-off notice there.
A sensible notice has four lines: the date, the parties and site address, a statement that you withdraw from the contract dated such-and-such under your statutory cooling-off right, and your signature. Email it and hand or post a copy, and keep the sent record.
What it costs
Cooling off is cheap, not free.
- Queensland: usually $100 plus an amount equal to any out-of-pocket expenses the contractor reasonably incurred before you withdrew.
- Tasmania: the contractor may retain $100 plus out-of-pocket expenses reasonably incurred up to the time of withdrawal, and must refund the rest of any deposit.
If a builder claims large expenses for the first few days of a contract, ask for receipts.
How the right is lost
By taking legal advice, in Victoria. Consumer Affairs Victoria recommends independent legal advice before signing a building contract, and then notes the consequence: if you get it, you no longer have the five days to change your mind. The logic is that an advised signature is a considered one. Take the advice anyway; it is worth more than the five days.
By the circumstances, in Tasmania. The Consumer Guide says there are certain circumstances in which you cannot rely on the cooling-off period, and lists them. Read that page of the Guide before you sign.
By time. Five business days is short. If you have doubts on the day of signing, do your thinking on day one, not day five.
Where there is no cooling-off
In the ACT the Government advises making sure you are ready to enter the contract before you sign, because you may not be able to change your mind without a penalty under the contract. The practical substitute is a contract clause: you can ask for a short withdrawal right, or make the contract conditional on finance or approval. A builder may refuse, but the request costs nothing.
Sources
- Contracts for residential building work, NSW Government
- Building contracts, Consumer Affairs Victoria
- Cooling-off period, QBCC
- Building, extending and renovating a home, Consumer and Business Services (SA)
- Residential Building Consumer Guide, CBOS Tasmania
- Hiring a builder, ACT Government
State rules mentioned here are set out in full on our licensing pages: New South Wales, Victoria, Queensland, South Australia, Tasmania, Australian Capital Territory.