Australian houses and the trades that keep them standing

Weatherboard JournalWEATHERBOARD JOURNAL

Bathrooms

Wet-area waterproofing: what the code requires

Tiles are decoration. The thing that keeps a shower out of the bedroom wall is a membrane nobody will ever see again, and the building code is exact about where it goes.

A shower in section with the waterproof membrane running up the wall and over the hob
The membrane runs across the floor, over the hob and up the wall. The tiles only protect it. Drawing: Weatherboard Journal.

A leaking shower announces itself late. First the paint blisters on the far side of the wall, in the hallway or the wardrobe. Then the skirting swells. By the time the carpet smells, the bottom plate of the wall frame has been wet for a year, and the repair is no longer a re-grout but a demolition. The Queensland regulator runs a series on the defects it sees most, and waterproofing has its own instalment.

The requirements themselves fit on a few pages. They sit in Part 10.2 of the Housing Provisions, the part of the National Construction Code 2022 that covers houses, and anyone can read them free on the Australian Building Codes Board's site. What follows is a plain-language tour, with the numbers.

Two words that are not interchangeable

The code uses two terms and means different things by them. A waterproof element stops water passing through. A water resistant element can get wet without being damaged but is not relied on as a barrier. Much of Part 10.2 is a list of which surfaces must be which, and a quote that says "waterproofing to bathroom" without saying where is glossing over that distinction.

The overall rule is in clause 10.2.1: building elements in wet areas must be protected with a waterproofing system, and that system must be waterproof or water resistant according to the clauses that follow.

The shower

The shower area gets the strictest treatment, as it should.

  • The floor of the shower must be waterproof, including any hob or step-down.
  • The walls must be waterproof to not less than 1800 mm above the floor substrate.
  • Wall junctions and joints inside the shower must be waterproof for not less than 40 mm either side of the junction.
  • The junction between wall and floor must be waterproof.
  • Every penetration, meaning the holes for taps, the mixer and the shower arm, must be waterproof.

Two details in that list repay attention. The 1800 mm is measured from the substrate, the surface under the tile bed, so a membrane that stops at 1800 mm above the finished tiles has gone slightly higher than the minimum, and one that stops level with the top of a 1700 mm screen has not gone high enough. And the penetrations are where most showers actually fail. The membrane is painted beautifully across the open wall and then a tap body is pushed through a ragged hole with a smear of silicone around it.

The rest of the bathroom floor

Outside the shower, the answer depends on what the floor is made of. For concrete, compressed fibre-cement and fibre-cement sheet floors, the floor of the room must be water resistant. For timber floors, including particleboard, plywood and other timber-based sheet, the floor of the room must be waterproof.

That one rule decides a good deal of the cost of renovating an old house. A bathroom on a slab needs its shower waterproofed and the remainder treated more lightly. The same bathroom upstairs, or in a timber-floored cottage, needs the membrane across the entire floor, wall to wall. Where a flashing is used at the wall and floor junction, its horizontal leg must be not less than 40 mm.

There is a separate provision for floor wastes. Where one is provided to drain a bathroom or laundry floor, the floor, the floor and wall junction and the penetration must all be waterproof.

Baths, basins and laundry tubs

Around an inset bath or spa, the code asks for waterproofing to not less than 150 mm above the lip, waterproof junctions within 150 mm of the bath, and a waterproof shelf with a waterstop under the lip where the bath is set into a tiled surround. Taps and spouts that come through a horizontal surface must have waterproof penetrations.

For basins, sinks and tubs, walls must be water resistant to at least 150 mm above the vessel, for the width of the vessel, where it sits within 75 mm of the wall. Junctions where a vessel is fixed to a wall must be waterproof.

Laundries get one oddly precise rule. In any room with a washing machine, the wall from the floor to at least 75 mm above and 75 mm either side of the washing machine taps must be water resistant. Somebody on the code committee has evidently watched a tap washer fail behind a front loader.

The 2022 edition also added a clause for the handheld bidet spray, a fitting that turns a toilet compartment into a wet area. The floor of the room must be waterproof, and walls within a 900 mm radius of the spray's wall connection must be waterproof to 150 mm above the floor and water resistant up to 1200 mm.

Falls, and why the membrane is not the drain

Waterproofing keeps water out of the structure. It does not get water to the waste. That is the job of the fall in the floor, and a membrane laid dead flat under a level tile bed will hold a permanent puddle against the grout. Ask the tiler how the fall is being formed, in the substrate or in the screed, and where the membrane sits in relation to it. The answer tells you whether they have thought about where the water goes after it gets through the grout, which it always does.

Who does the work, and what you should be given

Waterproofing in a bathroom renovation is building work, and the ordinary licensing thresholds apply. In Queensland that means a QBCC licence for work valued over $3,300, in New South Wales a contractor licence over $5,000 including GST, and in Victoria a registered builder once the job is worth more than $10,000. Bathroom renovations nearly always pass those lines, and nearly always involve a plumber and an electrician, who need licences at any value.

Before the tiles go down, ask for three things. A note of the membrane product and the number of coats, which should match the maker's instructions. Photographs of the finished membrane, including each corner and each tap penetration, with something in the frame for scale. And whatever certificate or statement your state expects from the installer, which varies; your certifier or building surveyor will know. Twenty minutes of photographs is the only evidence anyone will have once the room is tiled.

The statutory warranties that attach to building work run for years after completion, six for major defects and two for others in New South Wales for example, and a failed membrane is the classic claim. The warranty is easier to rely on with a dated photograph than with a recollection.

Questions readers ask

Does the whole bathroom wall need to be waterproofed?

No. Under Part 10.2 the full-height requirement, 1800 mm above the floor substrate, applies to the walls of the shower area. Elsewhere the code asks for water resistance in set zones, such as 150 mm above a basin that sits within 75 mm of the wall. Many tilers waterproof more than the minimum, which does no harm.

My bathroom has a timber floor. Does that change anything?

Yes. On a concrete or fibre-cement floor, the room floor outside the shower need only be water resistant. On timber, particleboard or plywood, the code requires the floor of the room to be waterproof.

Sources

  1. NCC 2022 Housing Provisions, Part 10.2 Wet area waterproofing, Australian Building Codes Board
  2. Who must hold a QBCC licence, Queensland Building and Construction Commission
  3. Home owner hub, Queensland Building and Construction Commission
  4. General building work, NSW Government
  5. Contracts for residential building work, NSW Government