What a defects period is, and what it is not
In brief
A defects period, often called a defects liability or maintenance period, is a term in your contract during which the builder returns to fix faults that appear after handover. It is separate from the statutory warranties, which the law imposes regardless of the contract and which last far longer: six years for major or structural defects in NSW, the ACT and Tasmania, and five years in South Australia.
Builders talk about "the defects period" as though it were the whole of their responsibility. It is the smallest part.
Two layers of protection
The contract layer. Most building contracts contain a clause giving a set period after practical completion, commonly some months, in which the owner lists faults and the builder comes back to fix them. The length is whatever your contract says. Read the clause for three things: how long it runs, how you must notify defects, and whether any money is held back until it ends.
The statutory layer. Separately, each state's building law writes warranties into every residential building contract. The NSW Government's wording is that even if these warranties are not written into the contract you sign, the law says they still apply. In the ACT, any contract term that tries to limit the statutory warranty is void.
The warranties in New South Wales give a fair picture of what is promised: the work will be done with due care and skill and in accordance with the plans and specifications; materials will be suitable and, unless otherwise stated, new; the work will comply with the law; it will be done with due diligence and within the time stated or a reasonable time; and where the work is a dwelling, it will be reasonably fit to live in.
A builder who says "you're out of your defects period" six months after handover is describing the contract layer. The statutory layer has years to run.
How long the statutory warranties last
| Jurisdiction | Period | Source wording |
|---|---|---|
| NSW | 6 years for major defects, 2 years for all other defects | From completion; a further 6 months applies if loss appears in the last 6 months |
| ACT | 6 years structural, 2 years non-structural | Structural includes weatherproofing of external walls |
| Tasmania | 6 years | From practical completion |
| South Australia | 5 years | Owner has up to five years from completion to take action |
| Northern Territory | 6 years structural, 1 year non-structural | The effective period for applying to the Commissioner |
Queensland expresses its protection mainly through the Home Warranty Scheme, which covers work for 6 years 6 months but with short claim windows. A structural defect must be claimed within 3 months of your first becoming aware of it. A non-structural defect must be noticed within 6 months of substantial completion and claimed within 7 months.
Victoria's new Home Warranty, for contracts signed from 1 July 2026, uses similar bands: up to 6 years for major defects and up to 2 years for other defects after completion.
When the clock starts
Everything runs from "completion", so the definition matters. New South Wales sets it out. Work is complete when it meets the requirements of the contract. If the contract does not define completion, the work is complete when it can be used for its intended purpose and is free of major defects, and the date is the earliest of handover, the last day the contractor did work other than fixing minor defects, the issue of an occupation certificate, or 18 months after an owner-builder permit was issued.
In Tasmania the contractor must give you written notice of the date of practical completion within 10 business days. Keep that notice. It is the first page of any future claim.
Using the defects period well
- Inspect properly at handover and again a few weeks before the contract period ends. Seasonal faults, such as a door that binds in winter or a gutter that overflows in a storm, need time to show.
- Notify in writing, with photographs and dates, in the way the contract requires.
- Give the builder reasonable access to fix the items. A builder locked out of the house has an excuse.
- If the builder does not come back, the regulator's complaint process is the next step. Do not wait: time limits for complaints can be shorter than the warranty itself. In Tasmania, inspection orders are only available for two years after the Certificate of Completion.
Later owners
Statutory warranties generally travel with the house. Victoria's implied warranties transfer to a new owner for up to 10 years from completion of the work, and the ACT's example is a buyer four years after completion who has two years of structural warranty left. If you are buying a recently built or renovated home, ask for the completion date and the builder's details.
Sources
- Contracts for residential building work, NSW Government
- Resolving building disputes, NSW Government
- Statutory warranties, ACT Government
- Residential Building Consumer Guide, CBOS Tasmania
- Building, extending and renovating a home, Consumer and Business Services (SA)
- Get defective or incomplete work fixed or paid out, Northern Territory Government
- Time limits for cover and claims, QBCC
- What Home Warranty may cover, Building and Plumbing Commission
- Implied warranties and domestic building insurance checklist, Consumer Affairs Victoria
State rules mentioned here are set out in full on our licensing pages: New South Wales, Australian Capital Territory, Tasmania, South Australia, Queensland, Northern Territory.